Project Management - Preventing Project Slips


Can Project Managers prevent projects from slipping?

Ask a techie to come up with a schedule for a specific list of activities, and more often than not, he/she will present a fairly accurate estimate. Some activities might be underestimated, others overestimated, but overall, the plan will be fairly accurate.

However, something happens to these estimates between the time the techie writes them down and the time the Project Manager publishes a baseline project schedule. That "something" is why projects slip.

Projects tend to slip for two reasons. Either Project Managers don't account for derivative activities such as vacation days when planning the overall project schedule, or they simply succumb to the pressure from management to compress the schedule.

The case surrounding derivative activities is well documented here or on The Project Mangler (www.projectmangler.com), so I won't spend any more time on it. The case surrounding management pressure is not.

Management Pressure

Assuming your techies have estimated each task and that you've considered derivative activities, your project schedule should be accurate. Aggressive, but realistic.

Now, present this schedule to the management team, and 8 times out of 10, the feedback you'll get is "that's too late". Eight times out of ten, you'll be asked to revise the schedule and shorten it.

Project Managers are all too familiar with the project triangle. We know we can shorten a schedule by either (a) reducing the scope of the project, or (b) adding more resources to it. Unfortunately, management either hasn't seen that triangle or, more likely than not, simply chooses to ignore it.

Consequently, Project Manglers who are more interested in pleasing upper management than keeping honest have come up with their own universal algorithm for shortening project schedules. Take the number of days that need to be cut from the schedule, divide it by the number of major milestones, and then deduct that number from the duration of each milestone. In other words, if a project comprising of 4 major milestones is estimated to last 6 months, but you need to reduce it by one month, you'd take 20 days, and divide it by 4. Take the answer (5), and deduct it from the duration of each milestone. And voila! Works every time.

And at the end of the project, either your techies save the day (by working evenings or weekends) or the project slips.

Conclusion

Can Project Managers prevent projects from slipping? Absolutely. Just stop publishing overly optimistic schedules.

1. Get your techies to help estimate the duration of each development task.

2. Add time to the overall project schedule to account for derivative activities.

3. Don't succumb to pressure from management

And last but not least?

4. Stick to the basic principles behind the project management triangle. In other words, don't be a Project Mangler.

Luc K. Richard is the founder and editor of The Project Mangler, a Web site dedicated to turning techies into managers. He invites you to visit http://www.projectmangler.com to download articles, project management tools, templates and checklists.


MORE RESOURCES:

RTT News

Waste Management 2Q profit flat, holds forecast
BusinessWeek
Waste Management Inc., the nation's largest trash hauler, said Thursday its second-quarter earnings were virtually flat as higher costs offset better ...
Waste Management sees flat 2QBizjournals.com
Waste Management Matches Est.Daily Markets
Waste Management's 2Q Boosted by Commodity PricesMorningstar.com
RTT News -RTT News -Dividend.com (blog)
all 22 news articles »


Daily Mail

Bedbugs Biting All Over US
WebMD
The survey, sponsored by the National Pest Management Association (NPMA), found that bedbug-related calls to exterminators have risen by 81% over the last ...
New York spends a bomb on rampant bedbug infestationDaily Mail
Blood-sucking bedbugs are multiplying, showing up across the nationNew York Daily News
New York City Battling Public Bedbug InfestationeMaxHealth
New York Times (blog) -CNN -Los Angeles Times
all 475 news articles »


Finance and Commerce

U.S. Bancorp, Nuveen in asset-management deal
MarketWatch
The deal is expected to boost Nuveen's assets under management to $175 billion from $150 billion, according to a press release. US Bancorp's FAF Advisors is ...
US Bancorp To Receive 9.5% Stake In Nuveen In Asset SwapWall Street Journal
Nuveen Investments Announces Strategic Combination with FAF AdvisorsMarketWatch (press release)
FAF Advisors to Combine with Chicago FirmBNET
Pensions & Investments -MutualFundWire.com (subscription)
all 46 news articles »



Money management a difficult lesson for NFL's rookie class
USA Today
As the neophytes learn playbooks, adjust to new cities and try to prove capability at a higher level, Vincent and others warn that money management ...

and more »


Apartment Investment and Management Company Declares Quarterly Dividend on ...
MarketWatch (press release)
Aimco is a real estate investment trust that is focused on the ownership and management of quality apartment communities located in the 20 largest markets ...

and more »


RTT News

Ameriprise shares soar on strong profit
Minneapolis Star Tribune
The financial firm got a big boost from its April acquisition of Columbia Management, but the deal leaves it more exposed to the stock market's gyrations. ...
S&P Lifts Ameriprise Outlook As Earnings Improve Further >AMPWall Street Journal
Ameriprise Financial Soars on Earnings SurpriseTheStreet.com
Ameriprise 2q profit nearly triplesBusinessWeek
Zacks.com -Reuters -Morningstar.com
all 67 news articles »


Quest Software Reports Second Quarter 2010 Results
MarketWatch (press release)
Furthermore, as announced previously, our acquisition of Volcker Informatik strengthens our Identity and Access Management solutions. ...
Epicor(R) Reports 2010 Second Quarter ResultsMarketWatch (press release)
Callidus Software Announces Second Quarter 2010 ResultsMarketWatch (press release)
Cumulus Reports Second Quarter 2010 ResultsMarketWatch (press release)
MarketWatch (press release) -PR-USA.net (press release) -PR Newswire (press release)
all 56 news articles »


Lazard 2Q Net Beats Views, Asset Management Jumps
Wall Street Journal
The asset-management arm, which has expanded in the past year to help balance the company's more-volatile financial advisory business, reported a 42% ...
Lazard outpaces rivals as merger fees riseFinancial Times
Lazard Posts $53 Million Profit for Second QuarterNew York Times (blog)
Lazard Q2 Profit Rises 58%; Tops EstimateDaily Markets
Morningstar.com -Reuters -MarketWatch
all 45 news articles »


Perkins Investment Management and Janus Launch Income-Focused Balanced Strategy
MarketWatch (press release)
Perkins will be responsible for the day-to-day management of the equity allocation and Janus will be responsible for the day-to-day management of the fixed ...

and more »

Google News



MaineBannerExchange

home | site map
© 2006